County approves change orders to extend courthouse project and record fairgrounds electrical work
Sep 2, 2026
The board approved a completion-date extension (change order #3) for the courthouse interior door and card reader project and approved a consolidated change order for electrical work at the county fairgrounds, citing field discoveries and subcontractor scheduling issues.
The full story
Facilities Manager Kevin Jolley (speaker 13) asked the board to approve change order #3 on the prevailing-wage contract with Convergent Technologies LLC (construction contract 6869) to extend the courthouse project completion date from Aug. 21 to Sept. 30 because subcontractor schedules delayed work. Jolley told commissioners the contractor expects to finish by the adjusted date and asked the board to authorize the change.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →