Hydrant tests show possible need for tank or pump; suppression could add $200K–$400K

Sep 30, 2026

Hydrant flow tests yielded varying results; staff warned that inadequate flow could require a pump, storage tank, or both, potentially increasing courthouse suppression costs by $200,000–$400,000. Commissioners asked for additional testing and coordination with Greenville and Fuller Fire.

The full story

Staff and River City reported on hydrant flow testing performed Sept. 22 and Sept. 25 to assess options for a courthouse fire suppression system. Staff said readings may have been affected by the City of Greenville filling tankers during the first test and that subsequent testing showed variable pressure across different hydrants.