Commissioners approve two courthouse change orders, table one pending options
Sep 30, 2026
River City presented three change orders totaling $16,158 for courthouse work (catwalk extension, restroom vents, LED ground floodlights). The board approved PCO 17 ($6,825) and PCO 19 ($5,851) and tabled PCO 18 (restroom vents, $3,482) to explore options that might reduce roof penetrations and cost.
The full story
River City representative Travis Evans briefed the board on three proposed change orders for the courthouse renovation. He said PCO 17 would extend a catwalk to service a new third‑floor HVAC unit so technicians could reach equipment without removing ceiling materials; PCO 18 would vent restroom exhaust fans through the roof to comply with current building code; and PCO 19 would replace existing ground floodlights with LED fixtures.
Staff summarized costs: PCO 17 (catwalk extension) $6,825; PCO 18 (restroom exhaust vents) $3,482; PCO 19 (LED ground floodlights) $5,851 — a $16,158 total and leaving $6,630.50 in contingency funds. "This change order would extend that catwalk over... so the technician can walk all the way to the end of the unit and back," Travis Evans said, explaining the serviceability benefit.
Commissioners voted to approve PCO 17 and PCO 19 and to table PCO 18 while staff examines if fewer roof penetrations or alternative venting arrangements could meet code and reduce impact to the new roof.
Written with AI from the event video and transcript. Check it against the source ↓