Selectboard questions contractor timeline for Pomfret Road slide project
Jul 16, 2025
The Selectboard raised concerns that Northwoods' email suggesting a mid-September start or completion conflicts with the RFP requirement that work be finished before Sept. 1; the chair will follow up with Northwoods and staff will consult VTrans about scheduling and bidder fairness.
The full story
Chair Benjamin Brickner said the Selectboard received an email from Northwoods indicating a mid-September start or completion date for the Pomfret Road slide project that appears to conflict with the RFP’s requirement of completion before Sept. 1. The board flagged the apparent ambiguity as problematic for procurement and schedule compliance.