Supervisor reports progress on new township hall; retaining wall work completed
Jan 7, 2026
Supervisor Ridenour told the board that ground tubes are in place, plumbing inspected, and concrete scheduled for the new township hall, with the building package expected Jan. 4, 2021; a retaining wall at Gross property was finished and a $10,000 guarantee check returned.
The full story
Supervisor Ridenour provided a construction update on the township hall, saying the crew "have placed the ground tubes and the cost is around $3,000" and that plumbing lines have been approved with concrete work scheduled to finish by the end of the week. He told attendees the building package is expected to arrive Jan. 4, 2021.