Council signs off on Banner Valley sidewalk adjustments, netting a modest decrease
Oct 9, 2024
Oct 9, 2024
Council approved two change orders for the Banner Valley sidewalk project: change order No. 10 reduced cost by $11,660 (110 fewer feet of slot drain) while change order No. 12 added $1,580.08 to pour a thicker curb/sidewalk edge, leaving a net decrease overall.
The full story
Council approved two change orders for the Banner Valley sidewalk project that together slightly reduced the project's cost.