Pumping Station project delayed; $80,430 inspection amendment tabled pending USDA documentation

Nov 5, 2025

GMB engineers reported the Pumping Station project is behind schedule and proposed an amendment for up to $80,430 for full‑time USDA-required inspection; the council tabled the amendment and requested documentation from USDA before taking up the amendment in December.

The full story

Jason Lytle and Andrew Lynch of GMB updated the council on the Pumping Station project's schedule, saying substantial completion had been scheduled for Nov. 29, 2025 with 30 additional days for final completion but the project is running behind and may complete in January 2026. Mr. Lytle presented an amendment to the owner‑engineer agreement requesting up to $80,430.00 for additional full‑time inspection services, which he said were required by USDA.