Council hears plan for expanded road program as staff propose 30‑year local‑road cycle

Sep 22, 2026

Public Works staff proposed increasing crack sealing and seal coating and moving toward a 30‑year local‑road replacement cycle, and identified expensive drainage and culvert projects (Center Street) that drive much of the capital ask.

The full story

Naomi (speaker 16) and Public Works staff presented a detailed capital‑improvement plan that separates sidewalks, drainage and paving costs to clarify why paving a single mile can be expensive. Naomi said: "Our roads look pretty good. We we evaluate roads based on a PASER rating system, which is a visual inspection of the concrete."