Engineer details wastewater upgrade progress, potential 19-day delay
Oct 5, 2026
Oct 5, 2026
Village engineering staff reported 8–9% contractor completion to date, a negotiated $21,000 contract credit, pending SBR equipment arriving mid‑October, and a potential 19‑day delay tied to bat‑habitat tree removal and digester solids that required extra work.
The full story
Village engineering staff gave a technical update on the wastewater treatment plant upgrade, walking trustees through the existing process and the elements being replaced or repurposed, including a new grit removal vortex, sequencing batch reactors (SBRs) and a disc-filter system.