Council approves $11,835 decrease to Calvin Park lift station contract
Oct 5, 2026
City Engineer Justin Peterson told the council a contractor adjustment to alignment reduced the Calvin Park Lift Station and Force Main contract by $11,835.85 to about $1.6 million; council approved the change order unanimously by voice vote.
The full story
City Engineer Justin Peterson presented a change order for Project No. 2428 (Calvin Park Lift Station and Force Main) that reduces the contract by $11,835.85, producing a new contract price of roughly $1,600,000. Peterson said the contractor proposed an alignment adjustment that resulted in savings for the city.