Board considers pausing driveway work while River Park East infrastructure is designed

Sep 28, 2026

Members proposed pausing driveway and other right‑of‑way‑adjacent site improvements to avoid duplicative construction while River Park East stormwater, street and utility designs are completed; staff said design is expected to take 18–24 months and will survey 5th Avenue North and 13th Street North.

The full story

Board members raised concerns that completing driveway and site improvements now could be undone by the planned River Park East infrastructure project, which will replace stormwater, streets and utilities and may alter elevations.