Operations staff said Small Structure 04 components will begin arriving the week of the 7th and crews expect to set the structure before the November 1 target; board members discussed alignment, head walls and offloading logistics.

The full story

Operations staff told the board that the precast components for Small Structure 04 will begin to be brought in the week of the 7th and that offloading will take place on 303 or 500 East with additional loads on the day of setting. A contractor representative said crews hauled a lot of dirt over the weekend and that the project is on track: "The structures are scheduled to be... Start being brought in the 7th, this week."