Board pauses decision on ISC/IMDA maintenance contract pending contractor visit
Jun 6, 2025
Ladoga utility board discussed a proposed ISC/IMDA maintenance contract — a five‑year automatic renewal with per‑meter charges and a materials fund — but voted to table the decision until a utility representative can provide quotes and clarify costs.
The full story
The Ladoga utility board debated whether to join an ISC/IMDA maintenance contract that staff said could include per‑meter charges and a materials fund, then voted to table the item until a utility representative, "Gary," can provide detailed quotes.
Committee member (S4) opened the agenda item by saying the meeting would address "IMDA and their maintenance contract, with ISC." Committee member (S3) told the board the contract as described would be "a 5 year contract automatically renewing for 5 years unless canceled a year in advance," and noted the board might need an interconnection ordinance to implement parts of the arrangement.
Board members quoted several cost figures during discussion but flagged arithmetic inconsistencies. S4 said "It was about a $101,119" as an annual figure; S3 said it boiled down to "$170 per meter per year" and S5 gave the count "655 meters" and calculated a materials‑fund total of "$19,650 a year." One speaker also read a line that "for the service core, it's $1.75 per year at 655 meters, which is is a $114,625," language the group treated as conflicting with earlier totals.
Concerns included whether large material purchases ("If the cost of materials is gonna be 5,000, it's not covered by the generic maintenance," S3 said) would classify as capital rather than maintenance, and whether the town’s cash flow could support the contract. Several members expressed interest in wholesale discounts for materials under a larger contract but emphasized the need for precise, reconciled cost figures before committing.
The board moved and seconded a motion to table the contract discussion until Gary can attend, take site visits, and provide a written estimate; the motion passed on voice vote. Members said they will revisit the item after Gary’s report and any required ordinance language is identified.