Board signals support for downtown string‑lights project at roughly $55,000
Jun 15, 2026
Jun 15, 2026
DDA staff informed the board a contractor bid for remaining downtown string lights is about $55,000 (higher than a prior $40,000 estimate); members gave informal assent to proceed and discussed timing and materials.
The full story
Staff told the board the contractor’s current estimate to finish the string‑lights project is just under $55,000 — higher than an earlier $40,000 figure — primarily because of underground utility work and base excavation. The board did not take a formal roll‑call vote but provided a head‑nod level of support with conditions about timing and impact.