Board refuses final acceptance of Castine Point Phase 6 pending developer fixes
Jun 4, 2025
City engineer reported significant punch-list items — pump station gauge issues, a local road failure and unfinished ditch work — and the board voted to meet with developers and withhold project acceptance until the contractor completes the outstanding items.
The full story
Long Beach's Mayor and Board of Aldermen declined to accept Castine Point Phase 6 as complete after the city engineer described multiple outstanding punch-list items and a failed roadway segment. David, the city engineer, told the board several items remain open and recommended the city not accept the phase until the developer and contractor fix them.