Council approves change order and budget reallocation for Mount Vernon Highway multiuse path
Oct 7, 2026
Council approved change order #7 to the Acceler/Excellor construction contract for the Mount Vernon Highway multiuse path (TS192) and a FY2027 budget amendment reallocating roughly $712,922 to cover quantity overruns largely tied to paving and wall quantities, bringing estimated contract total to about $13.23 million.
The full story
Public Works Director Marty Martin told the council that the Mount Vernon Highway multiuse path and intersection improvements (TS192) project reached substantial completion and staff recommended a time extension and a change order to address quantity overruns and other contract adjustments. Martin summarized third‑party conformance surveys and said plan takeoffs verified that field quantities matched constructed work.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →