Council approves change order and budget reallocation for Mount Vernon Highway multiuse path

Oct 7, 2026

Council approved change order #7 to the Acceler/Excellor construction contract for the Mount Vernon Highway multiuse path (TS192) and a FY2027 budget amendment reallocating roughly $712,922 to cover quantity overruns largely tied to paving and wall quantities, bringing estimated contract total to about $13.23 million.

The full story

Public Works Director Marty Martin told the council that the Mount Vernon Highway multiuse path and intersection improvements (TS192) project reached substantial completion and staff recommended a time extension and a change order to address quantity overruns and other contract adjustments. Martin summarized third‑party conformance surveys and said plan takeoffs verified that field quantities matched constructed work.