Council weighs preliminary engineering for Raleigh and Main streets in downtown plan
May 12, 2025
May 12, 2025
Council discussed phase 2 of downtown infrastructure, including construction cost estimates (Raleigh Street $1.25M–$1.5M; Main Street about $1.0M) and preliminary engineering (Raleigh $65,000; Main $52,700). Staff proposed funding engineering from next year’s local option sales tax and will return with a resolution.
The full story
City staff briefed the Ely City Council on downtown infrastructure phase 2 and sought direction on preliminary engineering and funding.