Select Board forms data-center working group to study zoning, utilities and community impacts
Sep 29, 2026
Amid public concern about data centers, the Select Board created a working group with representatives from sustainability, planning, board of health, electric & water, and a select board liaison; the group was given a sunset date of June 30, 2027 and a target to deliver recommendations by February 2027 if zoning changes are required.
The full story
Select Board members discussed public concerns about data centers and whether a moratorium or zoning changes are appropriate for Littleton. A board member said the town already has regulatory tools—special permits for structures over 50,000 square feet and water-use impact reports for users requesting more than 30 gallons per minute—but he proposed a working group to provide a comprehensive plan that addresses environmental, health and service concerns.