Board weighs data-center risks, moratoriums and local capacity
Oct 7, 2026
Oct 7, 2026
Consultants and supervisors discussed data centers — utility demands, noise and decommissioning — and whether the county should consider a moratorium; consultants advised preparing a plan before imposing limits and said site utility constraints make many large data centers unlikely in the county.
The full story
Data centers and related large energy projects dominated parts of the work‑session conversation as supervisors asked how the county should respond if proposals arrive.