Muscoda Board approves final payment and change order for downtown parking lot project

Nov 11, 2025

The board approved final pay application #2 to G Pro Excavating for $10,038.59 and Change Order #1 for $1,806.76; engineer Doyle said striping will be completed by the Village next spring.

The full story

Engineer Doyle presented the final pay request and Change Order #1 for the downtown parking lot project. The board approved final payment to G Pro Excavating in the amount of $10,038.59 and Change Order #1 for $1,806.76 to cover final material quantities; parking-lot striping will be completed by the Village next spring.