Control-tower chiller delivered; switch-over targeted Oct. 13 with short outage possible
Oct 7, 2026
Oct 7, 2026
The committee heard an update that the permanent control-tower chiller arrived in mid-September and contractors are targeting Oct. 13 to switch it in, possibly causing a brief (about 24-hour) loss of air conditioning in the tower.
The full story
The director updated the committee on the control-tower chiller replacement, saying bids had been received in February and the permanent chiller was delivered in mid-September. Contractors began connecting piping and equipment and are targeting Oct. 13 to switch from the rental chiller to the permanent unit.