Committee backs Blue Creek Drive concrete replacement project

Aug 4, 2026

The Public Works Committee recommended a due-pass for S-26-7-16 to reconstruct Blue Creek Drive (700 feet of pavement, 1,300 feet of curb and drainage) with a low bid nearly 11% under estimate; project funded with MVH funds and set to complete Sep. 24, 2027.

The full story

Traffic engineer Bill Rash told the committee that S-26-7-16 would replace 700 feet of concrete and 1,300 feet of curb and subsurface drainage on Blue Creek Drive east of Hadley Road. He said the low bid was nearly 11% under the engineer's estimate and that the project will be funded with MVH money, with completion scheduled for Sept. 24, 2027.