Mono County jail construction 57% complete; supply delays slowed masonry work

Oct 6, 2026

County engineer reported the jail project is about 57% through schedule with roughly $11.5 million spent to date; masonry block supply, grout mixture and steel ledger delivery created a month‑long delay on block walls but a contractor schedule review found float that may allow the project to finish on time.

The full story

County Engineer Kaylen Dodd told the board the jail project is roughly 57% through its scheduled time and that about $11.5 million has been expended to date (slide figure noted as stale). The project faced delays tied to masonry block supply and grout mixture issues; steel ledger deliveries were also late, prompting additional crew deployment to catch up.