Public Works reports ditching, culvert installation and Cedar Bluffs paving progress
Sep 22, 2026
Public Works updated supervisors that ditch-cleaning crews are working on County Road Main and County Road 27, culvert crews are installing twin 84'x42' CMPs on Project 880 (Ceresco West) and contractor work on Project 863 (Cedar Bluffs paving) has moved from patching County Road X to milling east from County Road 25.
The full story
The county’s Public Works Director told supervisors that dirt crews are cleaning ditches on County Road Main and County Road 27 and will move to County Road 20, while culvert crews are working on Project 880 (Ceresco West) installing twin 84'x42' corrugated metal pipes on County Road 20 & Ashland Road at a 15° skew. The director said crews plan to move next to County Road 28 & V for a culvert repair.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →