Draft data-center rules include decommissioning and financial-security requirements
Oct 8, 2026
Oct 8, 2026
The proposed zoning amendments add data centers as a regulated use (recommended in M2 heavy manufacturing), include detailed decommissioning plans and require financial security; staff also added a reference to the governor's PA grid commitment as current policy guidance.
The full story
Staff proposed a new set of performance standards for data centers and accessory data-center uses and recommended placing those uses in the M2 (Heavy Manufacturing) district. The draft includes decommissioning plans and a requirement for financial security to ensure cleanup when facilities are retired.