Fall Creek board approves contractor pay requests, authorizes change orders after unexpected soil problems

Sep 8, 2025

After contractors encountered unforeseen, unstable soil described as "like jello," the village board approved two pay requests totaling about $95,534 and authorized change orders to dig out buried topsoil and stabilize the site, with President Tim Raap authorized to sign.

The full story

The Village of Fall Creek on Sept. 8 approved two contractor pay requests and authorized change orders after staff reported unexpected soil conditions at an active construction site.