River Ridge approves $1.11 million drainage-improvement contract with added contingency

Apr 28, 2026

The board awarded Clark Construction Group a not-to-exceed $1,111,860 contract for four stormwater management phases after adding an extra 5% contingency to cover unknown unit costs; Charlie Krebs said contingency funds would cover tree removal, shrub replanting and capping existing golf-course drainage.

The full story

The River Ridge Community Development District board voted April 28 to award Clark Construction Group, Inc. the contract for four stormwater management phases (Oak Run, Turnberry, Palmetto Dunes and Seaside IV) in a not-to-exceed amount of $1,111,860, reflecting an additional 5% contingency added to contractor bids.