District reports drainage projects progressing; several trees to be replaced

Jun 23, 2026

District Engineer said four drainage-improvement sites are under construction with pipe, grading and sod work underway; completion is expected by the end of July, and staff noted the removal and replacement of 12 trees in Palmetto Dunes and six Cabbage Palms in Oak Run.

The full story

Charlie Krebs, District Engineer, told the Board that all four drainage‑improvement sites are under construction, with cleared sites, silt fences installed and pipe and grading work progressing. Krebs said that "all four sites are under construction; sites are cleared and silt fences were installed," and that Palmetto Dunes should be completed by the end of the week, with expected overall project completion by the end of July if grading remains on schedule.