Halstead reports sidewalk, Safe Routes and other infrastructure work underway
Mar 18, 2026
City Manager Ethan Reimer reported construction has started on the south side of the 6th Street sidewalk project (BCBSKS Pathways grant), Safe Routes to Schools Phase 1 preconstruction is expected in 2 4 weeks, and coordination continues on North Street railroad ROW; police staffing and emergency response updates were also included.
The full story
City Manager Ethan Reimer gave a multi-topic operations and capital projects update. He reported "construction has started on the south side of 6th Street Sidewalk connection project funded primarily by the BCBSKS Pathways grant," and said a preconstruction meeting for Safe Routes to Schools Phase 1 was likely in the next two to four weeks. Reimer also noted the city continues to coordinate with KDOT, BNSF and project engineers on North Street railroad right-of-way and easement approvals and that a tentative decision window for those approvals remains six to 12 weeks out.