Anna Maria cites $1.4M FDOT grant for Spring/Magnolia sidewalks; work delayed by cash-flow timing
Aug 11, 2026
Aug 11, 2026
Mayor Short confirmed about $1.4 million in Florida Department of Transportation (FDOT) grant funding remains for the Spring and Magnolia sidewalk project; staff said the schedule has been delayed mainly because the city must manage cash flow while waiting for grant reimbursements.
The full story
Commissioners discussed Pine Avenue and Spring/Magnolia sidewalk projects during the Aug. 11 workshop. Commissioner Gary McMullen raised concerns about the time required to complete Pine Avenue improvements and emphasized pedestrian-safety risks from poor sidewalks and crosswalks. Staff said the timing of improvements must be coordinated with the city's resiliency study to avoid constructing infrastructure that later must be removed or reconstructed.