CDD reports drainage work underway; trees to be removed and timelines set

Jun 23, 2026

District Engineer Charlie Krebs reported all four drainage sites are under construction with pipe, grading and silt fences in place; crews aim to complete work by end of July and will remove and replace 12 trees in Palmetto Dunes and replant six cabbage palms in Oak Run.

The full story

The River Ridge board heard an update June 23 on drainage improvements across four neighborhood sites. District Engineer Charlie Krebs said crews have cleared sites, installed silt fences, staged fill at Turnberry and laid pipe; if grading is finished, the project is expected to be completed by the end of July.