The county's hydraulic analysis for Middle Fork 10 requires a minimum 130-foot bridge; the department proposed a 130' x 26' concrete slab bridge with 15-degree skew. Poe 17 site survey is complete and hydraulic analysis is underway.
The full story
Engineer Jared Johnson told the Board that the Middle Fork 10 bridge replacement requires a minimum 130-foot span to meet hydraulic criteria; to reconcile site constraints the department proposed a 130'-0" x 26' continuous concrete slab bridge with a 15-degree skew.