Board accepts $101,708.87 return from Hayes Middle prime contract change order

Jan 20, 2026

Trustees approved a prime-contract change order that returns $101,708.87 from Hayes Middle School contingencies to the bond project fund; staff said those funds can be reallocated to Felton Elementary or other projects.

The full story

District construction staff presented PCCO-4 for Hayes Middle School and recommended returning $101,708.87 from owner and construction contingencies and held allowances back into the bond project fund. The presenter said the district originally held just over $200,000 and the change order reflects roughly half of that being returned; those dollars could be reallocated to Felton Elementary or other bond-funded needs.