CIP program manager reports 58 active projects; scheduled twice-yearly CIAC updates

Feb 2, 2026

CIP program manager Cindy Fro told the committee the city is tracking 58 active CIP projects across utilities, transportation, parks and facilities and described near-term deliverables and coordinated projects with Travis and Williamson counties.

The full story

Cindy Fro, the city's CIP program manager, told the advisory committee the CIP program is tracking 58 active projects: roughly 25 in utilities, 26 in transportation, five in parks and two in facilities. She summarized project phases (professional services procurement, bid, design, construction) and said about 30 projects are in design while 24 are in construction.