Selectmen approve two National Grid pole petitions, table third for updated sketch

Aug 25, 2026

The board approved National Grid petitions to relocate a pole on May Street and install a pole on Bigelow Road for road reconstruction and reliability; the South Main Street pole petition was tabled pending an updated sketch and further review.

The full story

The Board of Selectmen held a consolidated public hearing on three National Grid petitions to relocate or install utility poles at locations including May Street, Bigelow Road and South Main Street. Michael Macha, National Grid representative, explained the May Street request stems from a municipal road reconstruction project and the Bigelow Road request is reliability-focused.