Commissioners discuss Hunter Valley schedule, tree‑clearing window and possible bridge work
Aug 20, 2026
Commission members and staff said Hunter Valley Road construction realistically could start after tree-clearing season (Nov. 1–Apr. 1); the project may require a bridge if the crossing exceeds ~20 feet, otherwise box culverts could be used.
The full story
Staff and commissioners discussed timing and scope for the Hunter Valley Road project, including a seasonal window for tree work and whether the project will include a bridge or box culverts.
Lisa said the allowed tree-clearing window is Nov. 1 to April 1 and that, subject to contractor scheduling, construction could realistically start after tree work is completed. Commissioners asked whether design plans call for a bridge or multiple box culverts; staff indicated that a span over roughly 20 feet would likely be a bridge, while smaller crossings could use culverts.
Members also discussed linking the Hunter Valley work with nearby phases (Vernal Pike) so contractors could sequence tree clearing into construction to reduce mobilization time.