Engineer: piles likely at 70 Inlet Drive; techniques exist to limit vibration
Aug 21, 2026
Aug 21, 2026
The applicant's engineer said geotechnical borings have not yet been done for the lot at 70 Inlet Drive but that, based on nearby projects, piles are likely; he described pre-augering, helical piles and vibration monitoring to reduce neighbor impacts.
The full story
Joseph Kashuba of KBA Engineering Services told the board he had not performed soil borings on the specific lot at 70 Inlet Drive but, citing a nearby application that required piles, said it was likely that this site would also require piling.