Evergreen Elementary construction ahead of schedule, district told

Aug 17, 2026

District presenters said Evergreen Elementary construction is progressing quickly with footings and prefabrication underway; three contract amendments and two GMPs have been executed and GMP 3 (full project price) will be presented at the next meeting. Occupancy timeline is tight and commissioning is planned before and during occupancy.

The full story

District project staff told the board that work on Evergreen Elementary is "moving along extraordinarily well," with footings poured in most areas, formwork in place and some framing and floor work slated to begin soon. The presenter said the 100% DD set has been received and the team has executed three contract amendments and two GMPs; the full guaranteed maximum price (GMP 3) will be brought forward at the next board meeting so the board will know the complete project budget.