Solar Power Network representative told the board that interconnection costs to connect a solar project to NYSEG rose from about $410,000 to roughly $2.1 million; the company requested another six‑month extension while they negotiate and provide milestone documentation.

The full story

A representative for Solar Power Network asked the Fallsburg Planning Board for an additional extension under code 310‑7.11, saying interconnection costs to tie the project to the NYSEG system have increased substantially during negotiations.