Utility Department reports S. 4th paving, generator building nearing completion
Oct 5, 2026
Oct 5, 2026
Utility Department staff reported completion of S. 4th Street paving and brick work, upcoming parking work, planned tank removal and finishing of S. 3rd parking areas, and progress on a generator building, fuel tanks and transformers.
The full story
Doug Goracke, representing the Utility Department, updated the council on several infrastructure projects. He said S. 4th Street paving and brick work are complete and parking work is next; the department will remove a tank and finish parking areas on S. 3rd. The generator building is nearing completion, fuel tanks and transformers are set, and design work on the next project phase is underway.