Courthouse project advancing; roof and windows installed, framing underway

Jul 14, 2026

County officials reported the courthouse renovation is roughly one-third complete, with the roof and windows installed, framing on upper floors in progress and 35% of the construction budget spent so far.

The full story

County staff gave a construction update on the courthouse, reporting the roof is complete, windows are installed, framing for the first and second floors has been finished and third-floor framing is underway. "The roof is done. The windows are in," the speaker said, and staff noted the project is slightly more than 35% complete with about 35% of the budget spent to date. Work on the sally port and basement plumbing and finish work was described as ongoing.