Courthouse renovation reaches 35% complete; AV and security scope still being resolved

Jul 21, 2026

Project staff reported the courthouse is roughly 35% complete with roof and window installation finished and ductwork and framing progressing. The board discussed additional audiovisual and courtroom-sound needs that currently are not clearly in contract scope and scheduled a technical coordination meeting.

The full story

Project staff told commissioners the courthouse project is progressing on schedule: the roof work is complete, windows are installed, drywall and basement finishes are underway, and air handlers are staged on the roof while ductwork is being installed.