County awards summer paving and bridge contracts; Manatts low bidder at $3.31M

Mar 3, 2026

The board adopted resolutions awarding the F90 paving contract to Manatts for $3,313,210.36 and the B Avenue bridge to Herburger Construction for $698,486.36; both projects are expected to proceed this construction season.

The full story

Dallas County awarded two secondary‑roads contracts and set a public hearing for its five‑year construction program.

Secondary Roads staff told the board the Department of Transportation bid letting produced five bids for the F90 paving project; Manatts submitted the low bid at $3,313,210.36, roughly 3% below the engineer's estimate. Staff recommended awarding the contract to Manatts and authorized the county to execute the agreement; the board adopted resolution 2026‑0021. For the B Avenue bridge, three bids were received and Herburger Construction was the low bidder at $698,486.36; the board approved resolution 2026‑0022.

Officials said the F90 paving contract has about 65 working days (starting no later than May 17) and the B Avenue bridge about 60 working days; both are expected to occupy crews through much of the summer. The board also set a public hearing for the county's five‑year construction program on March 24 at 9:30 a.m.

Written with AI from the event video and transcript. Check it against the source ↓