Alliant, MidAmerican describe site design, augmentation and Franklin County example

Aug 25, 2026

Developers told Floyd County officials that BESS sites often use gravel bases, may remove topsoil, are frequently sited near substations, and can be augmented over time; the Franklin County site cited has about 70 containers and air‑conditioning was described as the loudest normal operation source.

The full story

Representatives from Alliant Energy and MidAmerican Energy described how BESS projects are sited and built, and how projects are scaled over time. Alliant said some projects purchase land for storage facilities while generation projects (solar/wind) are more commonly leased; developers described preparing a gravel equipment base and sometimes removing topsoil for construction.