Land Use Board deems Ansuya Enterprises site-plan application complete for phases 2–4

Jun 2, 2026

The board voted to deem Ansuya Enterprises' amended site-plan application for 1638 Rt. 31 North complete for Phases 2–3 (amended) and Phase 4 (initial), noting a Highlands consistency item will be reviewed by Town staff rather than the applicant.

The full story

The Town of Clinton Land Use Board voted on June 2 to deem Ansuya Enterprises, LLC's amended site-plan application for 1638 Route 31 North complete for further consideration.

Ken Carberry moved to deem the application complete as recommended in Bob Clerico's May 29 letter; Neil Viotto seconded. The motion passed with votes in favor from Neil Viotto, Craig Sailer, Jim Smith and Ken Carberry; Mayor Kovach was not eligible to vote. Attorney Kara Kaczynski, representing Ansuya Enterprises, told the board they had received the engineer's report and revised checklist and "feels that there is only one item on the list which is still incomplete."

Bob Clerico summarized his May 29 completeness letter and noted that checklist item #48, which referred to a Highlands filing, should be removed because the Town of Clinton now holds a Highlands consistency determination and Town staff (Jim Kyle) will review that item. Clerico outlined a mix of items to be granted permanent waivers, temporary waivers and conditional acceptances; the board directed that those conditions be addressed before any hearing or final approval.

Next steps: the application will proceed to hearing and technical review per the conditions in Clerico's report; the transcript does not record a final hearing date.