County engineer reports progress, erosion controls at Parkers Park Lot 35

Oct 8, 2026

The county engineer said erosion controls, berms, riprap/gabion baffles and slope drains are largely in place at Parkers Park Lot 35 but recommended pond cleanout after recent rains; contractor Faulkner/Falconer is on site and further inspections are planned.

The full story

The county engineer reported that construction at Lot 35, Parkers Park, is progressing rapidly and that perimeter erosion controls, slope drains and basin features are largely in place. The inspector said berms and vegetative stabilization are improving after recent rain and described gabion-basket baffle installations and risers supporting basin performance, though an inspection report recommended cleaning a wash plume from Basin 4 to preserve capacity.