Big Spring SD details summer facilities work: cameras, sealcoating and cellular boost
Aug 4, 2025
Aug 4, 2025
Administrators told the board that multiple summer projects — sealcoating, sidewalk leveling, brick repair, a cellular signal booster and a 107-camera replacement — are underway; camera installation is about 45% complete and the district expects final work on many projects by fall 2025.
The full story
Administrators presented a summary of summer facilities and technology work at the Aug. 4 meeting, saying the work was intended to improve campus safety and readiness for the school year. Mrs. B., speaking for facilities staff, described sealcoating and line painting at the high school and Mt. Rock Elementary and said the high-school campus work is complete while the Mount Rock work was expected to finish by the end of the day.