Utilities report AMI project completion, propose opt-out fee and major CIP reprioritization

Jun 10, 2026

Utilities staff said the AMI (advanced metering infrastructure) project finished under budget and ahead of schedule; they proposed an opt-out manual-reading fee, described a $161M reduction in six-year CIP through reprioritization, and flagged material cost pressures on upcoming projects.

The full story

Shane Koonce and James Lewis presented the Utilities department’s FY27 operating and capital plans, saying the department would be supported by six funds and that the operating budget excludes reserves and transfers. Koonce highlighted roughly $478,000 in operational savings tied to the AMI project and staff attrition savings of about $600,000.