City outlines multimillion‑dollar utility plan and explains recent rate changes
May 7, 2025
City staff described a master utility plan that identified multimillion‑dollar water and wastewater projects, noted a reduced GEFA loan award of $8 million (from a $24 million request), and said a rate restructure implemented Aug. 1 helps cover debt service and CIP needs.
The full story
City staff and consultants briefed the council on utility audits, funding, and the city's capital improvement program (CIP), describing work done under the Georgia Water Stewardship Act and the master utility plan prepared by Goodwin Mills Cawood (GMC).
Staff said the city asked GEFA for $24 million to address seven critical projects but was awarded $8 million after a debt‑capacity review. The award requires the city to prioritize projects and possibly postpone some work. Staff said three projects are drinking‑water related and four are clean‑water/wastewater projects. The council also heard that a water‑system audit and GMC's analysis drove a multimillion‑dollar CIP and that a new rate structure implemented Aug. 1 accounts for debt service and beginning CIP funding.
On social‑media questions about apparent water loss, staff noted the water audit processes account for main breaks, hydrant flushing, testing and other uses; staff said water loss is part of the overall assessment that led to CIP prioritization. The council discussed next steps: GMC will present rehabilitation plans for sewer and the master lift station at a May work session; the water‑treatment plant presentation is scheduled for June 2. Staff said loan and grant packages often require local matches (10–50%), so securing funding remains a multi‑year effort.
Written with AI from the event video and transcript. Check it against the source ↓