Solar array work to begin in June; CAT generator installation expected in October
Jun 1, 2026
Council heard a utilities update reporting a solar installation schedule that begins piling on May 18 with electrical work on May 24 and racking starting May 25, and a CAT backup generator due in October; crews have set poles and transformers and will seek state reimbursement for highway work.
The full story
Girard's utilities staff briefed the council on ongoing electrical and solar projects and damage responses. Staff reported 19 after-hours call-outs for power outages, installation of 13 poles and five transformers, and that the city will file for state reimbursement for highway-related work.